on-site report | hainan railway races against time to ensure the opening of the line and the eastern section of the ring island high-speed railway gradually resumes operation

2024-09-08

한어Русский языкEnglishFrançaisIndonesianSanskrit日本語DeutschPortuguêsΕλληνικάespañolItalianoSuomalainenLatina

nanhai.com reported on september 8 (reporter wang xiaochang, correspondent sun lei) at 4:30 a.m. on the 7th, as the super typhoon "makar" gradually moved away from hainan, in accordance with the work deployment, the hainan railway haikou comprehensive maintenance section immediately organized relevant workshops in the haikou area to conduct a comprehensive inspection of the haikou station in the rain overnight and cut down and cleared the fallen trees in the section.

clearing obstacles. photo provided by correspondent

at 10 a.m. that day, as the typhoon warning level dropped and its impact weakened, this section went into full action, racing against time to ensure the line was open.

the cadres and workers of this section wore raincoats and carried machetes, electric saws and other tools. they boarded rail cars and diesel locomotives to conduct a carpet-style inspection of the zhanhai line and hainan ring island high-speed railway and conventional railway lines to clear roadblocks.

clearing obstacles. photo provided by correspondent

during the inspection of the no. 57817 rail car from wanning to sanya on the eastern section of the ring island high-speed railway, the driver always maintained a low speed to allow the on-board personnel to observe the equipment and facilities. once any obstacles and equipment hazards were found, the driver stopped the car immediately and the professional personnel got off to deal with them.

"master, stop the train." the power supply personnel had sharp eyes and found that the contact network return line was dislocated at k265+415 meters down. after inspection, it was found that the insulator was broken, and it was replaced immediately. at present, more than 2,000 people have been invested in this section, 9 rail cars and 7 diesel locomotives have been put into operation, and 1 rail crane and 3 cranes have been dispatched.

clearing obstacles. photo provided by correspondent

according to statistics, this typhoon caused varying degrees of damage and impact to the equipment and facilities under the jurisdiction of the railway engineering, electrical and power supply departments. the more serious ones include the bending of the g01 power line pillar at haikou station, the awning at laocheng town station was blown off by the strong wind and caused damage to the contact network equipment, the hai'an south locomotive overhead lights fell on the line, and the anti-throwing nets of many overpasses were seriously damaged, all of which brought huge difficulties and challenges to the emergency repair work of equipment and facilities and the opening of the line.

it is understood that at 11:00 on the 7th, the collapsed overhead lights of hai'an south maintenance had been cut and cleaned. at 12:20 on the same day, the new pillars of the g01 power supply line of haikou station were assembled and anchored. the aluminum gussets on the contact network of laocheng town station took more than 9 hours to cut and clean. the contact network replaced 2 positioners, 5 hanging strings, reinforced two return lines, adjusted the parameters of 10 spans, and corrected 10 hard bends in the contact line. in order to ensure the early and safe opening of the line, the cadres and workers of this section carried dry food and worked around the clock, and the various systems and professional equipment and facilities are being repaired one after another.

repairing power facilities. photo provided by the correspondent

as of press time, except for the eastern section of the ring island high-speed railway, which will gradually resume operation at 11:00 on the 8th, the inspection, clearance and repair work of the zhanhai line and other railway lines under hainan's jurisdiction are still being carried out uninterruptedly. the railway department reminds passengers to pay attention to the railway 12306 website and station announcements to avoid delays in their trips.

starting from 11:00 on the 8th, the eastern section of hainan ring island high-speed railway will gradually resume operation

nanhai.com reported on september 8 (reporter wang xiaochang, correspondent fu zhuan) that the reporter learned from the haikou train depot of hainan railway that the eastern section of hainan ring island high-speed railway will gradually resume operation from 11:00 on september 8, while the western section of hainan ring island high-speed railway, haikou urban trains, and passenger trains in and out of the island will continue to be suspended on september 8.

the railway department kindly reminds you: the operation plans of hainan ring high-speed railway, haikou urban trains, and passenger trains in and out of the island have been dynamically adjusted due to the influence of typhoon weather. passengers who have travel plans in the near future are advised to pay attention to the railway 12306 website and station announcements before traveling to obtain the train operation information as soon as possible and make reasonable travel arrangements.