lotus: the construction of the wuhan headquarters has not stopped and has been in the construction preparation period for the past week

2024-09-27

한어Русский языкEnglishFrançaisIndonesianSanskrit日本語DeutschPortuguêsΕλληνικάespañolItalianoSuomalainenLatina

according to it house news on september 27, in response to rumors that the construction of the wuhan headquarters has been suspended, lotus today issued the "letter on the construction progress of the wuhan lotus technology headquarters", saying that the construction of the lotus headquarters has not been suspended.the construction work is currently progressing steadily as planned and has been in the construction preparation period for the past week.. lotus will promote the construction of its wuhan headquarters according to the plan.

it home attaches the full text of lotus’ letter of explanation as follows:

we have noticed that some media have recently published relevant reports on "the construction of wuhan lotus technology headquarters has been suspended", and lotus attaches great importance to it. thank you for your attention to lotus. the construction of lotus headquarters has not stopped. the construction work is currently progressing steadily as planned. it has been in the construction preparation period for the past week. the on-site conditions are as follows:

the managers of the curtain wall engineering unit reviewed the structural deviations of the building on site and improved safety protection work.

personnel from the supervision unit are assisting with safety and building re-testing and confirmation

general contracting company management personnel are on site to supervise safety and re-test and confirm building deviations

the detailed design drawings of the curtain wall project are being adjusted according to deviations.

the on-site curtain wall installation hanging basket has been installed in place and confirmed by third-party testing

the glass and profiles in the curtain wall sample area are expected to be installed on-site on september 27

please be aware of the above. lotus will promote the construction of wuhan headquarters according to the plan. thank you again for your attention!

public information shows that in 2020, geely group invested 8 billion in the construction of the lotus global smart factory in wuhan economic development zone. one year later, it established the lotus technology global headquarters in wuhan.

it is understood that the lotus global headquarters is built by geely with a total investment of 6.3 billion yuan. the project covers an area of ​​about 186 acres and a construction area of ​​about 390,000 square meters. the park is located in junshan new town, wuhan economic and technological development zone. it will be constructed in phases, including the first phase is expected to be delivered in 2024.

this project mainly builds the global operations management headquarters of lotus technology, which is responsible for the supply chain management, global marketing, and r&d design of lotus intelligent pure electric models in china. after completion, it can not only serve lotus in hannan at a close distance the vehicle project will also serve national and global geely and lotus projects.