congratulations! the first domestically produced f-class 50mw gas turbine has passed 2,000 hours of commercial operation

2024-09-19

한어Русский языкEnglishFrançaisIndonesianSanskrit日本語DeutschPortuguêsΕλληνικάespañolItalianoSuomalainenLatina

reporters learned from china huadian group that today (september 19), china's first independently controllable f-class 50mw heavy-duty gas turbine successfully passed 2,000 hours of full-load commercial operation, marking the maturity of my country's heavy-duty gas turbine commercial applications.
00:55
2000 hours of full-load commercial operation is an all-round test for gas turbines. such a test is not only a comprehensive test of the gas turbine's design, manufacturing, installation, commissioning and operation and maintenance capabilities, but also provides a guarantee for the independent control of my country's energy equipment.
gu zhixiang, chairman of guangdong huadian qingyuan company: after long-term efforts, the g50 gas turbine project now has the technical capabilities of domestic gas turbine fault early warning diagnosis and independent maintenance, and has made breakthroughs in key core technologies such as independent gas turbine remote monitoring, intelligent operation and maintenance, fault diagnosis and health management. it has established and improved the technical standard system for domestic gas turbine design, manufacturing, inspection and operation and maintenance, and solved the "bottleneck" problem of independent operation and maintenance of gas turbines.
the g50 gas turbine project, known as the "china's proud engine", has completed the entire process from construction to grid-connected testing in just 9 months since its construction started in 2022, and officially entered commercial operation in march 2023.